Microsoft 070-178 Questions & Answers - in .pdf
- Total Q&A: 70
- Update: May 30, 2026
- Price: $59.99
- Vendor: Microsoft
- Exam Code: 070-178
- Exam Name: Microsoft Project 2010, Managing Projects
- Features:
- Convenient, easy to study.
- Printable Microsoft 070-178 PDF Format.
- 100% Money Back Guarantee.
- Complete Microsoft Recommended Syllabus.
- Free 070-178 PDF Demo Available.
- Regularly Updated.
- Technical Support through Live Chat or Email.
- Exact Microsoft 070-178 Exam Questions with Correct Answers, verified by Experts with years of Experience in IT Field.
PDF is the abbreviation for Portable Document Format. It is an electronic file format regardless of the operating system platform. It is developed by Adobe company. PDF files are based on the PostScript language image model, no matter which printer can ensure accurate color and precise printing. In other words, PDF will fully reproduce each character, color, and image of originals.
Do you reconcile to be a person with a limited outlook who never makes any effort to transcend to the upper class? Do you want to pay the debt of the nature in obscurity without people ever knowing your coming to this world? If your answer is “no”, do choose our 070-178 exam dump torrent. We can assure you that our 070-178 : Microsoft Project 2010, Managing Projects training vce torrent will make a significant difference to you as long as you want to change your status quo. The following are some reasons why you ought to choose our 070-178 test training dumps.
High-quality exam files
Our 070-178 study materials are highly qualified in terms of two aspects. On the one hand, the exam files have lapped up great praise in this field as a result of their high hit ratio. That is to say, our Microsoft 070-178 test training dump is precisely targeted at the real exam, containing all the highly possible tested points, ranging from the classic points to the heated issues. There is almost no possibility that the questions showing up in the real test are not familiar to the customers. Therefore, customers who have made a purchase for our 070-178 study materials will answer questions handy with facility. One the other hand, due to high hit ratio, our TS 070-178 exam prep vce enjoys high pass rate. According to what is shown in the previous years, the overall pass rate for our 070-178 latest study pdf is about 98% to 99%. By far, no other study materials can supersede the record-high pass rate. That's why the majority choose to buy our 070-178 free study material.
In addition, we are also committed to one year of free updates and a FULL REFUND if you failed the exam.
Microsoft Project 2010, Managing Projects Sample Questions:
1. You use Project Professional 2010 to manage a software development project as shown in the exhibit. (Click the Exhibit button.)

You need to cancel the Develop prototype based on functional specifications task. You also need to retain all the information from the task. Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)
A) Inactivate the task.
B) Create a link from the Develop functional specifications task to the Review functional specifications task.
C) Set the tasks remaining work to 0 hours.
D) Delete the task.
E) Make the task 100 percent complete.
2. You need to select a view that allows you to use the drag-and-drop feature on the resource assignments and unassigned tasks. What should you do?
A) Select the Team Planner view.
B) Select the Gantt Chart view, split the window, and then select the Resource Usage view for the details pane.
C) Select the Timeline view.
D) Select the Gantt Chart view, and then click Assign Resources.
3. You have added two new tasks to your project. Both tasks are subtasks to a summary task. You need to update Baseline1 only for the two new tasks. What should you do?
A) Highlight the two tasks. Click Set Baseline and select Baseline1.Click the Selected Tasks radio button, select To all summary tasks, and then click OK.
B) Highlight the summary task. Click Set Baseline and select Baseline1.Click the Entire Project radio button, and then click OK.
C) Highlight the two tasks. Click Set Baseline and select Baseline1.Click the Selected Tasks radio button, and then click OK.
D) Highlight the summary task. Click Set Baseline and select Baseline1.Click the Selected Tasks radio button, select To all summary tasks, and then click OK.
4. You add a new summary task and detailed tasks to an existing project. You save the changes as Baseline2. You discover that Baseline2 only displays work hours for detailed tasks. You need to ensure that Baselinez displays work hours in the new summary task. What should you do?
A) ?Highlight the new summary task. ?Click Set Baseline and select Baseline2. ?Click the Entire project radio button, and then click OK.
B) ?Highlight the new summary task. ?Click Set Baseline and select Baseline2. ?Click the Selected tasks radio button, select From Subtasks into selected summary task(s), and then click OK.
C) ?Highlight the new detailed tasks. ?Click Set Baseline and select Baseline2. ?Click the Selected tasks radio button, select From Subtasks into selected summary task(s), and then click OK.
D) ?Highlight the new detailed tasks. ?Click Set Baseline and select Baseline2. ?Click the Selected tasks radio button, and then click OK.
5. All tasks in your project use the Auto Schedule mode. Several tasks are in progress. You need to reschedule all the remaining work on the project. You also need to achieve this goal without having rigid constraints set to your project's tasks. What should you do?
A) Click Update Project.
B) Click Move Project.
C) Change the Status Date field.
D) Click Calculate Project.
Solutions:
Question # 1 Answer: B,D | Question # 2 Answer: A | Question # 3 Answer: D | Question # 4 Answer: B | Question # 5 Answer: A |
Frequently Bought Together - Microsoft 070-178 Value Pack
$119.98 $69.99
50%
Price for 070-178 Q&A Value Pack (.pdf version and testing engine):
PDF is easy for reading, and Testing Engine can enhance your memory in an interactive manner. So many customers want to have both of them, for which we launched a large discount. Now buy the two versions of our material, you will get a 50% discount.
TS 070-178 Value Pack is a very good combination, which contains the latest 070-178 real exam questions and answers. It has a very comprehensive coverage of the exam knowledge, and is your best assistant to prepare for the exam. You only need to spend 20 to 30 hours to remember the exam content that we provided.
ITCertKing is the best choice for you, and also is the best protection to pass the Microsoft 070-178 certification exam.
Fast delivery after payment
The moment you have paid for our TS 070-178 training vce torrent, you will receive our exam study materials in as short as five minutes. I believe a seasoned veteran as you are, you have fast understanding about what time really means for those who make preparations for the test. Therefore, fast delivery is of great significance for them, which is also the reason why customers are prone to buy 070-178 study materials that can be delivered fast. To cater to the customers’ demand, our 070-178 : Microsoft Project 2010, Managing Projects latest study pdf provide them with timely dump “battery”, which must be in aid of them. Here under the guidance of our 070-178 study materials, the customers will attain their ambition in the near future.
Free renewal in one year
For the benefit of our customers, our Microsoft 070-178 exam prep vce offer free renewal to keep them informed of the latest questions in one year, which is utterly a privilege for them compared with that of other exam study materials in the field. What's more, our experts who are in charge of the renewal matters will be in the first time send the renewed dumps to mailboxes of their customers as long as the experts scent out the renewal. As a kind of people who is as vigilant to the renewal of 070-178 training vce torrent as a cat that is vigilant to the mouse, our experts will never miss any of the renewal in the TS 070-178 exam dump torrent.
if you still did not pass the exam, then as long as you provide us with the scan of authorized test centers (Prometric or VUE) transcript, we will FULL REFUND after the confirmation. We absolutely guarantee that you will have no losses.